As we know, Alton Towers are holding a press conference for The Smiler on Friday 17th May, with the speculation it will open on Saturday the 18th. With just over 5 weeks to go, let's take a look at what needs to be done:
Remaining track to be installed.
Electronics and ride operating system to be installed.
Audio and announcements to be put in place and tested.
Ride to be comissioned, tested many times, and to pass all clearances.
Any remaining theming to be applied.
Queueline and area to be paved or resurfaced.
Queueline fencing to be erected, plus theming including speaker placement.
Ride entrance to be created.
Staff to be trained on ride operation, despatch proceedures etc.
This is all I can think of but I'm sure there's more. But my main point is...is it possible? Half of me says yes, the other half no.